Primary Data Center Recovery

Estimated time to restore clinical information system operations in the event of complete loss of the primary data center

  All Respondents Most Wired Least Wired 
0-4 hours 14% 32% 5%
5-8 hours 7 9 6
9-24 hours 16 14 16
25-72 hours 27 36 21
73 hours to 7 days 18 6 15
8 days to 1 month 10 3 17
1 month + 3 0 8
Don’t know 5 0 12

Source: 2007 Hospitals & Health Networks’ Most Wired
Survey and Benchmarking Study